June 28, 2020

ARIBA IMPLEMENTATION AT MED-X MANAGING EARNED VALUE PDF

By using Ariba e-procurement platform, MED-X would reduce its spending and The project manager is lack of knowledge about earned value. Free Essay: Case Study II. ARIBA IMPLEMENTATION AT MED-X: MANAGING EARNED VALUE UNIVERSITY OF CONNECTICUT OPIM It is estimated that implementation of the Arabia e-procurement system will save the company $ million annually and also reduce spending streamline the.

Author: Samulmaran Viran
Country: Romania
Language: English (Spanish)
Genre: Art
Published (Last): 28 May 2005
Pages: 277
PDF File Size: 8.22 Mb
ePub File Size: 2.2 Mb
ISBN: 374-1-72890-671-5
Downloads: 80832
Price: Free* [*Free Regsitration Required]
Uploader: Yom

We use cookies to give you the best experience possible.

The implementation will also allow tracking of purchasing behavior and retrieval of historical information and help MED-X realize a significant return on investment. The project plan involves rolling out Arabia Buyer 7. Critical success factors for the project include a plan for organizational change effectiveness, quick resolution for business decisions affecting policy and vaalue of clearly defined project objectives.

Ariba Implementation at MED X: Managing Earned Value Paper

It is end of September and CIO has been told that the project cannot be finished on time. The Technical Infrastructure plan is over budget and behind schedule. The project manager does not understand why the project is delayed given that the overall project progress shows that the project is on schedule and under budget so far.

Since both activities are equally critical the project success, a delay in either one will delay the entire project.

Ariba Implementation at MED X: Managing Earned Value – Research Paper Example :

A separate earned value analysis of the individual plans showed us that the Software Customization plan is ahead of schedule and under budget and is, therefore, overshadowing the fact that the Technical Infrastructure Lana is not performing well and is delayed and over-budget. The project is actually delayed by 9 days at the current time.

Statement Of the Problem When managing a project, one might easily focus on the whole process and ignore important details necessary for project completion.

Any unexpected delay in critical activities can harm the planned schedule and cause delays of certain tasks and even the entire project. As a result, many project managers utilize the Earned Value Method as a tool to keep their projects on track. Never found anything wrong with the project while reviewing the budget variance and combined earned value reports; hence her surprise when she was informed that the project will not be delivered on time.

Martin, the project manager for this project is an expert in technical development, with very little experience in Earned Value Method. Our purpose is to help Martin find out which components are underperforming according to the plan, and make recommendations to avoid the same mistake from happening again.

The key tasks are to review the budget and earned value data for each task and figure what can be done to finish the project on time. Background All discussions about this analysis are based on a case from Kellogg School of Management: The main idea and strategy is using Earned Value Management Method to solve problem stated in the case.

  ENVIRONMENTAL ENGINEERING AND SANITATION BY JOSEPH SALVATO PDF

Most of the background knowledge comes from case itself while our solution is mainly based on the technologies of cost control which are introduced during lecture 4 by Professor Jose.

By determining if cost ACschedule UPand work accomplished EVE are progressing as planned, we created an integrated performance report which uses consistent, numerical indicators like C. The method we adopt is FEM. Earned Value Management is a project management technique for measuring project performance and progress.

We measure the project performance not only as imolementation whole, but also by performance of its components. Therefore, the statuses of the schedule and cost of technical infrastructure, software customization, and combined projects can be easily and clearly checked, respectively.

MS Excel is the main software we used in this analysis, and all the information came from the case. Result In order to understand why the project could not be delivered on time, we did an earned value management exercise as shown in the tables below. First We decided to focus implememtation the technical infrastructure and software customization components of the project because they earnex on the critical path.

As you can see in table 1the technical infrastructure component of the project is underperforming compared to the software customization.

The cost variance C. Earned value activity for the technical infrastructure component of the project On the other hand, when looking at table 2, we realize that the software customization component of the project is well ahead of schedule and under budget. The cost variance and eagned variance are both positive, C. This is confirmed by the fact that the calculated cost performance index and schedule performance index are above 1 Table 2: Earned value activity for the software customization component of manging project After doing the analysis for the separate components of the reject, we decided to do the earned value exercise for the combined components table 3 in order to understand the surprise reaction of the Arriba Terry Baker when she discovered that the project could not be delivered on time.

When looking at the earned value analysis for the combined critical component in the project, the project appears to be on track to be delivered on time. According to table 3, the calculated cost variance C. Those conclusion re umplementation by the Schedule Performance Index SIP and Cost Performance Index Cup value being above 1; confirming that the project should be delivered on time or even before the due date.

Earned value analysis for combined projects After the analysis of the two activities both separate and together, we determined that it will take an extra 9 days to complete the project as calculated in the table 4 below. We calculated the percent completion for the technical impplementation component of the project using the rolling earned value and estimated budget at completion for September 5 months.

  LIBRO DERECHO PROCESAL CIVIL JOSE OVALLE FAVELA PDF

Extra time needed to complete the technical infrastructure part of the project Conclusions and recommendations In general, based on the combined rolling ratios, the MED-X implementation project was not out of control and was performing well on the whole. According to the overall results, it was still under budget and ahead of schedule. However, when our team examined the components in details, we found that the implemsntation infrastructure setup was the main reason that undistributed to delaying and over-budgeting in terms of its negative schedule variance Aruba and cost variance C.

The project completion at the time was Moreover, the control ratio CRY less than one also implies the underperforming of technical infrastructure component in the project.

In spite of knowing the standard implementation technology earned value analysis template, to figure out what was going wrong, Martin should arlba kept checking the individual earned value in detail so that he could monitor which components or activities had exactly influenced or delayed the project and had immediate reactions toward the problems. For instance, he could have put more resources on the underperforming components right as soon as the initial problems appeared.

Implemenyation prevent this from happening Martin and his team should have implemented the following measures vakue the earlier phase Of the project: What should Martin do going forward?

Product details

Our team suggests that he ask for an extension or discuss the project scope with the CIO to determine whether there can be some compromises as a remedy. Otherwise, to meet the completion date, Martin can ask mrd-x more resources. For instance, our team assumes that 4. Five extra full time workers will be needed in order to complete the project on time. Accessed December 30, Managing Earned Value,” PaperAp. Managing Earned Value specifically for you. Leave your email and we will send you an example after 24 hours If you contact us after hours, we’ll get back to you in 24 hours or less.

Managing Earned Value Paper. How to cite this page Choose cite format: How about make it original? Sorry, but copying text is forbidden on this website. If you med-xx this or any other sample, we can send it to you via email. Arba Earned Value send By clicking “Send”, you agree to our terms of service and privacy implementztion. We’ll occasionally send you account related and promo emails.

Sorry, but downloading is forbidden on this website.